EEE会議(米国原子力事情:Indian Point原発の現状)....................................................031225


米国ニューヨーク州のIndian Point原発が抱える問題については、これまで数回にわ
たって詳しくご紹介してきましたが、その後状況は一向に好転せず、いままた、原子
力規制委員会(NRC)の最新報告によれば、同原発の2号機、3号機(1号機は3
0年来シャットダウンしている)は、過去12ヶ月間に、全米の他の原発に比べて約
3倍の頻度でシャットダウンしている(全米平均は年に0.64回)とのことで、テ
ロ攻撃の脅威のほかに、安全面でもいろいろ問題だらけのようです。それだけ周辺住
民の監視の目が厳しいということで、大都会の近傍に原発を作ることの困難さを物語
るものと言えましょう。詳細は次のNew York Timesの記事でどうぞ。
--KK

*******************************************

Indian Point Is Criticized for Shutdowns
   By STACEY STOWE

Published: December 25, 2003


The Indian Point nuclear plant had three times as many unplanned shutdowns
in a 12-month period as any other plant in the nation, an official of the
Nuclear Regulatory Commission said yesterday. The agency said in a report
released a day before that a failure to follow protocol, insufficient
quality control and poor contractor oversight contributed to the shutdowns
at the plant in Buchanan, N.Y.

The report, which was first reported yesterday by The Journal News, was
initiated after the plant's reactors ? Indian Point 2 and 3 ? experienced a
combined total of eight unplanned shutdowns in a period of a year and a
half, a spokesman for the regulatory commission said. The national average
for shutdowns at a power plant is 0.64 per year, he said.

The Indian Point plant, in northern Westchester County on the Hudson River,
has been a focus of concern since the terror attacks of Sept. 11, 2001. It
was later discovered that one of the hijacked planes had flown close to the
plant on its way to the World Trade Center.

The 47-page report, which examined shutdowns from late December 2001 to
August 2003, says diesel generators in offices at the plant failed during
the blackout of Aug. 14, forcing technical support and emergency response
crews to relocate and use contingency plans. Both systems were previously
identified as problematic but were never repaired, the report said.

"The failure affected their emergency response facilities, but in a
real-world scenario, there was no safety implication to that," said Neil A.
Sheehan, the spokesman for the regulatory commission.

The report, completed Oct. 24 after a one-month inspection, identifies six
problems at the plant, including poor preventive maintenance and failure to
follow emergency procedures and proper protocol in response to unplanned
shutdowns.

In one case, poor protocol during a shutdown resulted in improper handling
of pressure levels in the reactor coolant system, the report said. Each of
the findings was categorized by the commission as posing the lowest safety
risk in its four-tier category. Entergy Corporation, the New Orleans company
that owns Indian Point, has 30 days to issue a response to the report, Mr.
Sheehan said.

James Steets, a spokesman for Entergy, said the company plans to improve
oversight of its contractors, many of whom supplement its 1,500 employees by
working in such areas as high-voltage electricity repair and maintenance. He
said that the long inspection and ensuing report found what he called
relatively minor problems. "They really found very little," Mr. Steets said.
He added that the areas cited in the report either have been addressed or
are being addressed. "We're not where we want to be, but we're working
toward that," he said.

But at least one environmental group said the report was one more piece of
evidence that should lead to the shutting down of the plant. Kyle Rabin, a
senior policy analyst for Riverkeeper, the Hudson River watchdog group,
criticized both Entergy and the Nuclear Regulatory Commission for minimizing
the significance of the report's findings, which he said illustrate serious
safety issues at the plant.

"This is just more ammunition for elected officials representing the public
in this region to call for the closing of Indian Point," he said.

Mr. Rabin said the disclosure that the backup generators had failed on Aug.
14 contradicted a statement released by Entergy that said generators at the
plant had been operational. Mr. Steets said yesterday that the statement
referred to the emergency diesel generators used for the reactors, not in
offices.

One longstanding problem at Indian Point is the switch yard, an electrical
substation operated by Con Edison, where power is transmitted from the plant
to the power grid, the report said. Entergy has "failed to take appropriate
and timely corrective actions to avoid grid-related reactor trips," the
report said. At least half of the unplanned shutdowns can be attributed to
the switch yard or off-site electrical problems like the blackout, Mr.
Steets said.

"More strides should have been made by now," Mr. Sheehan said. The Nuclear
Regulatory Commission will conduct an annual inspection of Indian Point next
spring.

The plants at Indian Point, 2 of 103 operating reactors at 68 sites in the
nation, produce enough energy to power two million homes, Mr. Steets said.
There are three reactors, but Indian Point 1 has been shut down since the
1970's. Indian Point 2 and 3 are licensed to operate for the next decade and
are eligible to apply for license renewal, Mr. Sheehan said.